Home / Filtration / Case studies / Flexiparts
Filtration case study · Supply & certification

Three certified vessels,
documented before despatch.

Rapid-opening four-bag housings in SS304, mirror polished, Viton sealed — hydro-tested to 1 MPa held 30 minutes, with the certificate supplied alongside.

What this case study is, and is not. This is a documented supply case — what was specified, what was built, and what documentation came with it, all traceable to the manufacturer’s certificate and hydro-test report. We have not published operating results because we do not hold Flexiparts’ process data, and we do not publish numbers we cannot evidence.

The requirement

Three rapid-opening multi-bag filter housings for an Australian industrial installation, specified for frequent bag change-out with the documentation to satisfy a pressure-equipment review.

What was supplied

ItemSpecification
DescriptionRapid-opening four-bag filter housing
Drawing numberHLK4P2S-CC-F50
Quantity3 units
Design pressure0.8 MPa
Design temperature80 °C
Filter area2 m² across 4 bags
Overall size878 × 766 × 1300 mm
Shell materialSS304, ø508 mm
Welding & connecting materialSUS304
ConnectionsDN50 PN16 PL RF B, HG20592 / 304
Sealing materialFluoro rubber (Viton)
Surface treatmentInner and outer mirror polishing
Manufactured toJB4735-1997
Batch / completion202410017 · 9 December 2024

The testing

Each vessel was hydrostatically tested before despatch, to a procedure written against the German AD pressure-vessel rules (chapter 9, section 2.1):

  • Test pressure 1 MPa — above the 0.8 MPa design pressure
  • Hold time 30 minutes
  • Chamber volume 200 L
  • Result passed hydro-test and leak test, no leakage recorded
  • Certified 10 December 2024, responsible engineer named on the certificate
The documentation went with the vessels

Product certificate stating every parameter in the table above, plus the hydro-test report showing test pressure, hold time and result. That is what a pressure-equipment review asks for, and supplying it after the fact is far harder than specifying it before manufacture.

View the certificate & hydro-test report

Why the quick-open cover mattered here

The unit was specified as rapid-opening rather than bolted. On a housing changed frequently, the cover mechanism is the difference between a two-minute task and a twenty-minute one — and a bolted cover retensioned unevenly by a rushed operator is the most common cause of seal failure on this equipment.

What we would ask for next time. Where the installation is subject to Australian pressure-equipment registration or third-party inspection, that requirement is best raised at enquiry stage — documentation specified before manufacture costs nothing, and retrofitting it afterwards is expensive or impossible.

Specify the same thing

The vessel supplied here is a four-bag housing in the quick-open family. See the four-bag specification, the rest of the quick-open range, or send us your duty for a quote.

Need the same documentation trail?

Tell us the duty and whether the installation is subject to pressure-equipment review. We specify the certification before manufacture, not after delivery.